Get the code, the accounts and the data into the company’s name first, while the vendor is still answering email. Then prove you can build and release the application without them, have someone who did not write it read it, and only after that start changing it. The order matters because the vendor’s cooperation is the one thing in a takeover that runs out.
This applies whether the next team is your own or another firm. It is written for an application that is already in use. A project that stalled before it went live has a different first problem.
1. Get the code, the accounts and the data into the company’s name
This comes first because everything else depends on it, and because it gets harder every week after the relationship ends. Ask for all of it in writing, and check each item yourself.
- The source code, with its full history. A zip file of the latest version loses the record of who changed what and why. Ask for the repository itself, moved into an account the company owns.
- The hosting and cloud accounts. The company should be the account owner and the one that pays the bill. If the application runs inside the vendor’s own account, plan to move it.
- The domain, the DNS and the certificates. These are small, they are often registered to one person at the vendor, and losing one takes the application offline.
- Accounts with third parties. Payment processors, email and text services, mapping services, app store developer accounts, and every API key the application uses.
- The data and the backups. Get a current copy of the database, and find out where the backups go and who can restore them.
- Licenses. Paid components and libraries are sometimes licensed to the vendor and not to you.
Read the contract for what it says about who owns the code and what the vendor owes you at the end. If it is unclear, that is a question for counsel, and it is better asked while both sides are still talking.
2. Collect what the vendor knows while they will still tell you
Code tells you what the application does. It rarely tells you why, and it does not list what is half finished.
Ask for a recorded walkthrough with the developers who did the work, and pay for their time if the contract does not cover it. A few paid hours now are cheap next to weeks of working it out later. Cover these points.
- How to build it, test it and release it, step by step.
- What runs on a schedule: the nightly jobs, the imports, the reports that go out by email.
- What is known to be broken, and what the workaround is.
- What was started and not finished.
- Which decisions look odd, and what forced them.
- Who at your company they usually dealt with, and about what.
Keep it civil, even when the vendor has let you down. The purpose of the conversation is to get answers, and people who feel blamed give short ones.
3. Prove you can build and release it without them
Until you have done this, you do not know whether you can run the application on your own. Three checks settle the question.
- Build the application from the repository on a machine the vendor never touched.
- Release that build to a test environment and confirm it behaves like the live one. If it does not, the code you were given is not the code that is running, and you need to find out why before the vendor goes.
- Restore the database from a backup, once, into the test environment.
When all three work, end the vendor’s access and replace every password and key they held. Do it in that order. Cutting off access first is a common way for a takeover to go wrong, because the things you still needed from the vendor turn out to be things only their login could reach.
4. Keep it running as it is
The business will want the list of changes the old vendor never got to. Hold them for now. A team that does not yet understand an application should not be adding to it.
In this period, fix only what is urgent. Turn on monitoring if there is none, so that you hear about an outage before the users call. Decide who answers when it breaks at night, and write down how to restart it. How do you reduce key-person risk on a small IT team? describes the one-page version of that document.
5. Have it read before you decide what to do with it
Someone who did not write the application should read all of it: the architecture, the code, the data, the hosting, the security basics and the way a change reaches users. What Is a Software Audit, and When Do You Need One? covers what a read like that examines and what you get back.
The result is a decision about each part of the application: keep it and extend it, rework it, or replace it. Most systems do not need a ground-up rebuild. VisionLink Advisory Group came to us after it was unhappy with a previous development partner. In his review on Clutch, its president, Tom Miller, says the first work was to clean up and redo some of what the earlier developers had done, keeping what both sides agreed could be kept, before new development began.
6. Make the first change a small one
Choose a fix that users will notice and that touches little code, and take it all the way to production. One small release exercises the whole path: the build, the tests, the release, the rollback. It also shows the business that the application is in hands that can change it.
A takeover also does not have to begin with the big decision. Longshot Cameras had an app that freelancers had developed. In his review on Clutch, its founder, Clay Rhoden, says our work began with updates to that existing app for a new version of the company’s product, and that a new version of the app to replace the old one came later.
Then write down what the takeover taught you, while it is fresh, and make sure two people can do each step in it. If the application was built so that only its builder could run it, the takeover is the moment to end that. Why We Build on Mainstream Stacks and Plan for Handover describes what an application looks like when it is built to be handed over.
If the application you are inheriting is a project that never worked, Software Project Rescue: The Warning Signs and the First 30 Days is the closer fit.
Common questions
The vendor will not hand over the code. What can we do? Read the contract for what it says about who owns the code, ask for it in writing, and take a refusal to counsel. In the meantime secure what you can reach: the running system, the database, and every account that is already in the company’s name.
Should the new team rewrite it? Not as the first move. Have the system read first. A rewrite makes sense when the data model is broken or the platform is truly dead. Most systems do not need a ground-up rebuild.
How long should the old vendor keep access? Until you have built the application from your own repository and released it without them. After that, remove their access and replace every password and key they held.
Can our own team take it over? Yes, and the steps are the same. The questions are whether they have the hours, and whether it is built on technology they already work in.
If you want to know what you are taking on before you commit to it, a System Evaluation gives you written findings and a prioritized plan for a fixed fee.