How do you replace a technology vendor without losing the project?

Before you give notice, secure what the company has paid for, read the contract with counsel, and have the work read independently. Then choose the next team and pay for a short overlap.

Before you tell the vendor anything, make sure the company holds what it has paid for, read what the contract says about ending it, and have someone independent read what has been built. Then choose the next team, give notice, and pay for a short transition in which the two teams overlap. Projects are lost when notice comes first and the company finds out afterwards what it does not hold.

1. Check that replacing the vendor is the fix

A new vendor inherits the project’s problems along with its code. If nobody can say what “working” means, if decisions wait on someone in the business who has no time for the project, or if the first release was scoped as the whole system, the next team will stall in the same place.

Sometimes the team is missing a role, such as an architect or a delivery lead, and can finish once it has one. Replace the vendor when the cause is the vendor: you cannot see the work, the same defects come back, dates move with no explanation, or the people who knew the project have left it. Software Project Rescue: The Warning Signs and the First 30 Days lists the signs.

2. Make sure the company holds what it has paid for

Do this before any conversation about ending the contract. Asking for access to your own project is an ordinary request and needs no explanation.

  • The source code with its full history, in a repository the company owns.
  • The hosting and cloud accounts, with the company as the account owner.
  • A current copy of the data, and the location of the backups.
  • The designs, the requirements, the backlog and whatever documentation exists.
  • The accounts with third parties and every API key the system uses.

Check each one yourself by signing in. If the answer to a request is that you will get it at the end of the project, you have learned how the vendor sees ownership, and you should settle that before anything else.

3. Read the contract before you say anything

The contract decides how hard the transition will be. Look for these points.

  • How either side may end it, and how much notice is required.
  • What is owed for work that is in progress on the day it ends.
  • Who owns the work, and when ownership passes. Some contracts pass it only when every invoice is paid.
  • What help the vendor owes you during a transition, and at what price.
  • Whether the system depends on anything licensed from the vendor, such as a framework or a component of its own.

Take the contract to counsel before you give notice. If you are thinking of holding back a payment to get the code released, ask counsel first what that does to your rights.

4. Have what was built read before you choose anyone

You need to know what you have before you can ask anyone to finish it. The read should say, part by part, what works, what can be built on and what has to be redone, and it should say so in writing. What Is a Software Audit, and When Do You Need One? describes what a read like this covers.

Written findings give every candidate the same starting point, so their proposals can be compared. A candidate that quotes a price for finishing work it has not read is guessing, and so is one that recommends starting again without reading it. Most rescues keep more than people expect.

5. Choose the next team before you give notice

Knowledge is lost in the gap between vendors. The outgoing developers are moved to other work, and their answers get shorter after that.

VisionLink Advisory Group planned its move. In his review on Clutch, its president, Tom Miller, says a member of his team found us when the company began planning its transition away from its previous developers, researched firms, narrowed the search to two or three teams and interviewed them.

Ask each candidate three things beyond the usual questions.

  1. How would you spend the first month, and what would you need from the outgoing vendor?
  2. What in the written findings would you keep, and what would you redo?
  3. Can we speak to a client whose project you took over from another firm?

Questions to Ask a Software Development Partner Before You Sign covers the rest.

6. Give notice, and pay for a short transition

Tell the vendor plainly, in the way the contract sets out, and keep it civil. You need their answers for a few more weeks, and people who feel blamed give short ones. Ask for these in writing.

  • All work in progress committed to the repository, finished or not.
  • A recorded walkthrough of how to build, test and release the system, with the new team present.
  • The list of known defects and unfinished items.
  • A named person who will answer questions for an agreed period.

Pay for this time if the contract does not cover it. A few paid hours from the people who wrote the code cost less than weeks of the new team working it out.

Keep the vendor’s access until the new team has built the system from your repository and released it. Then remove the access and replace every password and key the vendor held.

7. Restart on a smaller plan, and tell the business what to expect

The old dates belonged to the old plan. Take new ones from the new team after it has read the work. Make the first release a small one that goes all the way to production, because it exercises the whole path and shows the sponsor that the project is moving again.

Tell the sponsor before the switch what it will look like. For some weeks the company pays two teams and sees little that is new. A sponsor who was told this in advance will recognize those weeks as the plan, and one who was not will take them for a second failure.

Common questions

Should we tell the vendor we are talking to other firms? Not until the company holds the code, the accounts and the data, and counsel has read the contract. After that, tell the vendor directly and in the way the contract sets out. They should not hear it from someone else.

Can the new team use what the old vendor built? Often a good part of it. Nobody can say how much before reading it, which is why the independent read comes before the choice of a new team.

How long should the two teams overlap? Long enough for the new team to build the system from your repository and release it once without help. End the overlap when that has happened, whatever the calendar says.

What if the vendor will not cooperate? Secure what you can reach, put every request in writing, and take a refusal to counsel. A new team can work from the code, the running system and the database when it has to. It is slower, and it can be done.

If you need that independent read before you decide, a System Evaluation gives you written findings, a recommended path and a fixed proposal for the next step, for a fixed fee.