A proper handover moves three things to the team that will run the system. The first is control of the code, the accounts and the data. The second is the working knowledge, in a short set of documents the receiving team has already used. The third is a handful of written decisions about who owns the system and who answers when it breaks. The handover is finished when the receiving team has released a change and restored a backup without help, which is usually some time after the documents are delivered.
This applies whether the system is going from a vendor to your own team, from one vendor to another, or from the project team that built it to the people who will support it.
Start while the people who know the system are still working on it
A handover is a piece of work with its own plan. It needs a named person on each side, a date, and hours set aside for the people handing over, who are usually busy with something else. The handovers that go badly are mostly the ones that started in the last week.
It is also joint work. On one of our own projects the client brought more of its team in-house as the work went on, and said afterward that the two sides could have planned those transitions better together. The outgoing team knows what has to be passed on, and the receiving side decides who will receive it and when those people are free.
Move control into the company’s name first
Knowledge is no use to a team that cannot get in. Before anything else, confirm that the company holds each of these, and that no single person or vendor does.
- The source code with its full history, in a repository the company owns.
- The hosting and cloud accounts, with the company as the account owner and the one that pays.
- The domain, the DNS and the certificates, with the dates they expire.
- Accounts with third parties: payment, email and text services, app stores, and every API key the system uses.
- The data and the backups, including where the backups go and who can restore them.
- Licenses and support contracts for paid components, in the company’s name, with their renewal dates.
When we build a system, the code is in the client’s repositories and the cloud accounts are the client’s, so at handover this step is a matter of checking the list. Why We Build on Mainstream Stacks and Plan for Handover gives the reasons.
The documents the receiving team needs
Ask for a short set that people will read. Each document answers a question the new team will have in its first month.
- An overview of the system. One or two pages and a diagram: what it does, who uses it, where it runs and what it connects to.
- How to build, test and release it. Step by step, starting from a clean machine. Following this document is how you find out whether the code you hold is the code that is running.
- How to operate it. How to tell whether it is healthy, how to restart it, how to restore it, and what breaks most often.
- What runs on a schedule, and what it exchanges with other systems. Nightly jobs, imports, file transfers and integrations, each with the person to call at the other end.
- A list of access. Every account, key and certificate, who holds it, where the secret is stored and when it expires. The secrets themselves stay in the password manager.
- Known problems and unfinished work. The open defects with their workarounds, and anything that was started and not completed.
- The decisions that look odd, and what forced them. Without this, a new team spends weeks undoing something that was done for a reason.
- Contacts. The owner in the business, the vendors, and the person to call at each.
A small system can be handed over with less: the codebase and its libraries, documentation for setup and configuration, and a session with the receiving developers on how to maintain and monitor the service.
Have the receiving team do the work before the date
A document is untested until someone has followed it. Before the handover date, the receiving team should do each of these while the outgoing team watches.
- Build the system from the repository and release a small change to production.
- Restore the database from a backup into a test environment.
- Run the scheduled task that matters most, such as the month-end job.
- Take the first call when something breaks, with the outgoing team as the second call.
Every question the outgoing team has to answer along the way becomes a line in the documents. When all four are done, the receiving team can run the system. If they cannot be done yet, move the date.
The decisions to write down
The documents describe the system. These decisions say who is responsible for it after the date, and they are the part most often left unsaid.
- Who owns the system. One named person in the business who decides what it should do, and one in IT who is responsible for keeping it running.
- Who answers when it breaks, from which date and during which hours. If a provider is taking over support, this is the service level in its agreement.
- What the outgoing team still owes after the date. How long they will answer questions, what happens to a defect found in the first weeks, and what that time costs.
- What is accepted as it is. The known problems the receiving team agrees to take on, listed by name, so that nobody argues about them later.
- Whether changes are frozen around the date. A release in the same week as a handover leaves nobody sure who caused a problem.
- When the outgoing team’s access ends. It ends after the receiving team’s first release without help, and every password and key the outgoing team held is replaced at that point.
- What marks the handover as complete. The four tasks above, done, and the agreement of both owners.
Mistakes that show up after the outgoing team has gone
- The documents arrive on the last day, and nobody has tried to follow them.
- Access is removed before the receiving team has released on its own.
- The date falls in the busiest period for the business, such as month-end.
- The owner in the business hears about the handover after it has happened.
After the handover, check that the knowledge has not simply moved from one person to another. How do you reduce key-person risk on a small IT team? covers how to get a second person able to do each task.
Common questions
How long should a handover take? It depends on the size of the system and on how much is already written down. Set the end by the tasks and let the calendar follow: the handover is done when the receiving team has released a change, restored a backup and handled a problem on its own.
Do we need complete documentation before we can hand over? No. A short set that the receiving team has used is worth more than a complete set nobody has opened. Start with how to release, how to recover, and who holds which access.
Should the outgoing team stay available afterwards? Yes, for a period that is written down, with a named person and an agreed cost. Questions come up in the first month that no document anticipated.
The outgoing vendor is not cooperating. What then? Secure control first: the code, the accounts and the data. Then offer to pay for a few hours of walkthrough if the contract does not cover it. If the vendor will not hand over what the contract says is yours, take that to counsel.
If you are on the receiving end and want an independent account of what you are being handed, a System Evaluation gives you written findings for a fixed fee.