How do you recover a stalled technology project without causing a second failure?

Stop adding to it, find out why it stalled and what you actually have, decide what to keep with a cost on each option, and replan around one smaller release.

Stop adding to it, find out why it stalled and what you actually have, and decide what to keep before anyone writes new code. Then replan around one smaller release, and change whatever caused the stall. A recovery becomes a second failure when the middle steps are skipped: a new team starts building at once, on work nobody has examined, toward the same unclear goal.

This applies to a software build, an ERP implementation, a data platform or an integration program. The steps are the same.

How a recovery turns into a second failure

The pressure in a recovery is to show movement quickly. That pressure leads to a few decisions that look like progress and repeat the first failure.

  • The team is replaced and the plan is kept. The new team inherits the same scope, the same date and the same way of making decisions.
  • Work restarts on the first day. Nobody has checked whether what was built can carry more.
  • Everything is thrown away. The parts that worked go out with the parts that did not, because nobody separated them.
  • The original date is kept. That avoids a hard conversation now, and the date is missed again.
  • Scope is added. New features are promised to justify the extra money, on top of work that is not yet stable.

Each step below is there to prevent one of these.

1. Stop the project from getting worse

Pause new features. Do not send the team home: you need them for fixes and for answers. If any part of the system is already in use, keep it running.

Then make sure the company holds what has been built. Ask in writing for the source code and its history, the environments, the cloud and vendor accounts, the backlog and whatever documentation exists. You will need all of it for the next two steps, and the response tells you something about the relationship.

Tell the sponsor that new work is paused, and give the date on which you will come back with findings.

2. Find out why it stalled

Do this before you decide anything about people, because the cause decides the fix. Replacing a team does not repair an unclear goal. These are the causes to look for.

  • Nobody can say in a paragraph what “working” means, so the definition of done keeps moving.
  • The first release was scoped as the whole system.
  • Decisions wait on someone in the business who has no time for the project.
  • The team is missing a role, such as an architect or a person who runs delivery.
  • An integration or the data turned out to be harder than the plan assumed, and the plan was never changed.
  • Problems were known inside the team and were not reported.

Ask the people doing the work, one at a time, including the vendor’s developers. They usually know.

Express Freight Handlers saw the first cause with an earlier developer. In his review on Clutch, its president, Jim Wissing, says that with the firm the company used before us the software was designed as the work went along, and that the result was disorganized and poorly structured. His advice to other buyers is to make the goal clear to everyone before the work starts.

3. Get an independent read of what was built

Someone who did not build it should read all of it: the code and configuration, the data, the environments, the way a change is released, and the security basics. They should also use it. An item reported as done is done when a person can use it for the job it was meant for.

The read should say, for each part, whether it works, whether it can carry more, and what it would take to finish. Include the current team. They hold most of the facts, and a read that feels like a trial gets guarded answers. What Is a Software Audit, and When Do You Need One? describes what a read like this covers.

4. Decide what to keep, with a cost on each option

There are three options: salvage what exists and finish it, rework the parts that cannot carry the load, or restart with what you have learned. Ask for each one with a cost, a schedule and a list of what is kept. The money already spent is not an argument for any of them.

Most recoveries keep more than people expect.

5. Replan around one smaller release

The original plan has already failed once, so do not resume it. Write a new one.

  1. Write one paragraph on what “working” means to the people who will use the system. The release is measured against that paragraph.
  2. Choose the smallest release those people could use for real work, and put the riskiest part of it first.
  3. Take the new dates from the team that will do the work, after the read. A date carried over from the old plan has no basis.
  4. Fix the budget and let the scope flex inside it, so that a surprise changes the list of features and not the invoice.

Why We Build a First Release, Not an MVP covers how to decide what goes into that release.

6. Change what caused the stall

If the project is run the way it was before, expect it to stall again. Match the change to the cause you found in step 2.

  • A named person in the business who can make decisions, with time set aside for the project.
  • Working software shown every week to the people who will use it.
  • One backlog that both sides can see.
  • The code and the accounts in the company’s name from here on.
  • A status report that says what is slipping, in plain words, while it is still cheap to fix.

The Projects That Failed, and What Changed describes the weekly routine we adopted after our own failures. If you are not yet sure that the project is in trouble, Software Project Rescue: The Warning Signs and the First 30 Days lists the signs.

Common questions

Should we replace the vendor? Not until you know why the project stalled. Sometimes the team was missing an architect or a delivery lead and can finish once it has one. Sometimes a clean handover is the right answer. The independent read tells you which.

How much of what was built can be kept? Nobody can say before reading it. Most recoveries keep more than people expect. The read answers the question part by part: the data model, the workflows, the screens and the integrations.

How long does a recovery take? The independent read is the part with a known length. Our System Evaluation takes one to four weeks, depending on the size and complexity of the system and how quickly access is given. What follows depends on what the read finds, and a date given before then is a guess.

What do we tell the executive team while this is going on? Tell them what you know, what you do not know yet, and the date you will bring a plan, and keep to that date.

Is it ever right to cancel the project? Yes. If the reason for the project has gone, or finishing it would cost more than the result is worth, stopping is a sound decision. Make it from the written findings.

If you need that independent read, a System Evaluation is the fixed-fee first step, and it ends with written findings, a recommended path and a fixed proposal for the work.