Lift and shift when the application is sound and the reason to move is the hardware under it or a support date. Replatform when the application is sound and you want to stop running its servers and database yourself. Rebuild only when the application itself is the problem. Decide one application at a time, and check first whether it should move at all.
What each term means
- Lift and shift moves the application to cloud virtual machines as it is. AWS calls this rehosting and defines it as moving an application to the cloud without making any changes to the application.
- Replatform moves it and changes what it runs on, with little or no change to the code. The example both vendors give is a SQL Server database on a server you manage becoming a managed database service.
- Rebuild writes the application again for the cloud. Microsoft’s guidance on choosing a migration strategy describes it as a full redevelopment, for when the existing system is obsolete or modernizing it is not feasible.
The vendors list more options than these. Microsoft names eight and AWS names seven. Between replatforming and rebuilding sit refactoring and rearchitecting, which change the code or its structure without starting over.
| Lift and shift | Replatform | Rebuild | |
|---|---|---|---|
| What changes | Where it runs | Where it runs, and the database or hosting under it | The application |
| What stays the same | The code, the operating system, the database and how it is released | The code, apart from small changes | The data and the business rules you choose to keep |
| What it fixes | Aging hardware, a lease that is ending, a host you want to leave | The same, and the patching, backups and failover of the parts the provider now runs | Software that cannot be changed safely or no longer fits the business |
| What it does not fix | Anything wrong with the application, or an operating system that is going out of support | Problems in the code or the data model | Unclear requirements: the business still has to say what the system should do |
| Effort and risk | Lowest | Moderate, mostly testing against the new platform | Highest |
| What your team runs afterward | The same servers as virtual machines: patching, backups and monitoring are still yours | Fewer servers, and more services the provider runs | A new application and its operations |
Check first whether the application should move at all
Three cheaper answers come before any migration path.
- Retire it. AWS suggests looking for applications that have had no inbound connection for 90 days. Run that check before you pay to move anything.
- Keep it where it is. An application tied to equipment on a plant floor, or one that was upgraded last year, can wait.
- Replace it with a product a vendor runs. This is the usual answer for commodity functions such as email and file sharing.
When lift and shift is the right choice
The application is stable, nobody plans to change it much, and the pressure is on what is under it: hardware at the end of its life, a lease that is ending, or a date. Windows Server 2016 is the current example. Microsoft’s lifecycle page puts the end of its extended support at January 12, 2027.
A move does not answer that date. The same operating system on a cloud virtual machine is just as far out of support, so plan the operating system upgrade as part of the move or directly after it. The same page lists three further years of Extended Security Updates. They buy time, and the upgrade is still ahead of you. Windows Server 2016 reaches end of support on January 12, 2027 covers the options for each server.
Microsoft’s guidance gives two cautions that are worth repeating. Do not rehost a workload that already has performance or reliability problems, because the move carries them along. And rehost only when you are confident the workload will not need modernizing within two years, to avoid doing the work twice.
When replatforming is the right choice
The application is sound, and the cost is in keeping it running: patching the database server, managing backups, planning for a failover. Moving the database to a managed service and the web tier to an application hosting service hands that work to the provider.
It needs testing before you commit. A managed service does not offer everything a server you control does. Anything in the application that depends on access to the operating system, on a file path, on a server-level job or on one exact version has to be found and changed. That list is usually short for a conventional business application and long for one that has been customized for twenty years.
When a rebuild is the right choice
The application is the constraint. The source code is missing or will not build, the framework is one nobody supports, the data model no longer matches the business, or every change breaks something else.
A rebuild is the most expensive of the three paths. AWS says of rearchitecting, the nearest of its seven strategies to a rebuild, that it is the most complex and costly, and for a large migration it recommends moving first and modernizing afterward wherever that is possible.
Dunkin & Associates, an insurance brokerage that serves community banks, is an example of the application being the problem. In his review on Clutch, its EVP of Operations, Doak Dunkin, says the system that connects the banks to the insurance carrier dated from the 1990s and was causing them a lot of trouble. He describes the order of the work: a process to determine the scope, then the new system, then help bringing the banks onto it.
A rebuild does not have to end in one cutover. When we modernize a system, we do it in slices behind the running version, so there is no single date on which everything changes at once.
Which path we would pick
For a sound business application, replatform the database and the hosting where the application allows it. Lift and shift what cannot be changed before a deadline, and write down what happens to it next and when. Rebuild only when someone has read the code and can show why the other two will not work.
Record the decision for each application: the path, the reason, the date and the owner. Legacy System Modernization covers the same decision from the business side, for an executive team.
Common questions
Is lift and shift a waste of money? No. It is the right choice when the application is stable and the reason to move is hardware, a lease or a support date. It disappoints when it is expected to improve the application, because the same application arrives with the same problems.
Can we lift and shift now and modernize later? Yes, if the later work has a date and a budget before the move starts. The risk is that the move uses up the money and the attention, and the application then runs unchanged in the cloud for years.
How do we know whether an application is sound enough to move as it is? Check four things: the source code is in hand and builds, someone can release a change, it runs on versions that are supported or can be upgraded, and its connections to other systems are known. If one is missing, find out why before you choose a path.
Does every application have to take the same path? No. Decide one application at a time. A typical portfolio ends up with some of each, and a few applications that are retired and never moved.
If you cannot tell which path an application can take, a System Evaluation is the fixed-fee first step: an independent look at its architecture, code and infrastructure, with a prioritized plan and a recommended path.