Move first a workload that is low in risk and still teaches your team the whole process: a test environment, or an internal system with few connections whose owner can live with a bad afternoon. Before that, build the foundation everything else will sit on: accounts, sign-in, the network, backups and monitoring. Leave the system the business can least afford to lose until the team has a few moves behind it, unless a deadline such as an operating system going out of support decides otherwise.
Decide what is moving at all
Start with a list of every workload: what it does, who owns it in the business, the operating system and database it runs on, what it connects to, and how much an outage would hurt. Which of your systems and processes depend on one person? helps with the items nobody thinks to list.
Not everything on the list should move. Microsoft’s guidance on choosing a migration strategy and AWS’s description of the same choices both include treatments that involve no move: retire the workload, replace it with a product someone else runs, or keep it where it is for now. Turn off what nobody uses before you plan anything else, because a server you retire never has to be moved.
Each workload that remains gets one treatment: move it as it is, move it onto a managed service with small changes, or rebuild it.
Build the foundation before the first workload
The first workload arrives in an empty environment, and how that environment is set up decides how every later move goes. Have these in place first.
- Accounts and ownership. The cloud account is registered to the company, with at least two named administrators and a company address for billing and security notices.
- Sign-in. People sign in with the identities they already have, with multi-factor authentication, and administrator rights go to named people.
- The network. A private connection between your site and the cloud, address ranges that do not collide with the ones on site, and name resolution that works in both directions.
- Backups and recovery. Where backups go, how long they are kept, and a restore that someone has run.
- Monitoring and cost. Alerts that reach a person, and a budget alert so the first bill is not a surprise.
Write down how it was done, because the fifth workload will be set up by copying the first.
What makes a good first workload
Microsoft’s guidance on planning migration waves recommends starting with workloads that are less complex and lower in risk, moving non-production environments before production, and scheduling critical systems after the team has shown it can do the work. That is the order we would use too.
A good first candidate has most of these.
- Few connections. It does not feed or read from many other systems.
- A willing owner. Someone in the business knows the date, agrees to it and will test the result.
- Room for a short outage. It has a quiet period, and a problem during the move would be an annoyance.
- A supported platform. It runs on a current operating system and a database the cloud provider supports as it is.
- A way back. The original stays untouched until the new copy has proved itself.
- Something to teach. It resembles what you will move later. A file share is easy to move and teaches little about moving an application with a database behind it.
The same guidance suggests adding one or two more complex workloads to the early waves for that last reason. They expose the problems the critical systems will have while the stakes are still low.
Move things that depend on each other together
An application and its database talk to each other constantly. Put one in the cloud and leave the other on site, and every query crosses the connection between them. The application gets slower and has a new way to fail.
Map what each workload depends on before you set the order: databases, file shares, integrations, scheduled jobs, reports that read the database directly, license servers, and printers or equipment on site. The people who use and support the system know some of this. The rest shows up when you record the network connections each server makes over a period that includes a month-end. Workloads that depend on each other closely move in the same step.
When a deadline sets the order
Sometimes the calendar picks the first workload. Microsoft’s lifecycle page gives January 12, 2027 as the end of extended support for Windows Server 2016, and a system still running on it may have to be moved or upgraded before you would otherwise have touched it. Windows Server 2016 reaches end of support on January 12, 2027 covers the options for each server. Hardware at the end of its life and a datacenter lease that is ending have the same effect.
When a critical system has to go early, give it more protection: a rehearsal of the move in a test environment, a longer period of testing by the people who use it, and a rollback you have tried. Microsoft’s wave guidance makes the same allowance for business deadlines such as a hardware refresh.
Why the first moves should leave the application’s design alone
For the early moves, change as little as possible. When a workload changes its location and its design at the same time and something goes wrong, you cannot tell which change caused it. AWS’s guidance for large migrations calls refactoring the most complex of the migration strategies and recommends modernizing after the migration is complete.
There are exceptions, and Microsoft’s strategy guidance names them. Moving a workload as it is does not fix a performance or reliability problem it already has, and it suits a workload you expect to leave alone for at least two years. If the application is already due for a rewrite, plan the modernization and the move as one piece of work, and schedule it after the simple moves. Our guide to legacy system modernization covers that decision.
How to run each move
We move systems in slices, with a tested rollback, while the business keeps running. The steps for each slice are the same.
- Agree the date and the outage window with the owner in the business, away from month-end and the busy season.
- Write down, before the day, what would make you roll back and who decides.
- Rehearse the move in a test environment and time it.
- After the cutover, have the people who use the system check it, including its integrations and scheduled jobs.
- Keep the original, switched off and intact, until the new copy has been through a full business cycle such as a month-end close.
- Then remove the original. A server left running after its replacement is live is paid for twice.
After each move, write down what took longer than expected and change the plan for the next one.
Common questions
Should we move everything at once? No. Moving in groups lets the team learn on the early ones and limits how much can go wrong on one day. Moving everything at once only makes sense for a very small environment where every system depends on the others.
Should the most important system go first, to get the risk over with? Usually not. The first moves are where the team finds the problems in its own process, and you want those found on a system the business can do without for an afternoon. If a deadline forces a critical system early, rehearse the move and test the rollback first.
Should we modernize an application while we move it? For the first moves, no. Change the location and leave the design alone, so that a problem has one possible cause. Plan modernization as its own piece of work unless the application cannot be moved as it is.
How do we find out what a server is connected to? Ask the people who use and support it, read its configuration and its scheduled jobs, and record the network connections it makes over a period that includes a month-end. Expect to find a connection nobody mentioned.
If a system on the list is old or undocumented enough that nobody is sure how it would behave after a move, a System Evaluation gives you an independent written account of its architecture, infrastructure and risks for a fixed fee.