You hold a vendor accountable on a project by settling four things in writing before the work starts: the result, the person who answers for it, what the price covers, and who owns what is produced. Then you check the same short list every week while the work runs. A contract gives you a remedy after something has gone wrong. The weekly check is how you find the problem while it is still small.
The lists below are written for project work, such as an application, an integration, a migration or a data platform. If you only have time for part of them, take the named person, the weekly report with budget beside progress, and the code in your own repository.
What to get in writing before the work starts
- One named person who answers for the result. Ask for a name, a role and a phone number. If the answer is “the account team”, nobody in particular answers for it.
- A result you can test. Each deliverable has a description of what it does when it is finished, and a person on your side who accepts it. “Phase 1 complete” cannot be tested.
- What the price covers, and what changes it. The proposal says what is included, what is left out, and how a change is priced and approved. Fixed budget, fixed price, or hourly explains where the risk sits in each kind of contract.
- Who does the work, and where they are. Ask whether they are the vendor’s own employees and whether any part of the work is passed to another company. You need to know who has access to your systems.
- Your ownership of the code, the accounts and the documentation. The work is done in repositories and cloud accounts that belong to your company, from the first day. If the vendor holds the only copy, every later conversation with it is harder.
- How defects are handled. Know before the first one appears who fixes a defect during the build, who fixes it after launch, and what each costs you. Who Pays for Bugs in Custom Software? goes through the usual arrangement.
- How either side ends the engagement. The agreement states the notice period, what is handed over, and in what condition. This is much easier to agree before signing than during a dispute.
- What the vendor needs from you. That is usually a decision-maker, access to systems, and answers within an agreed number of days. Write these down too, because a vendor that is waiting on you cannot fairly be held to its dates.
Questions to Ask a Software Development Partner Before You Sign has the longer list of questions for the selection itself.
What to check every week while the work runs
- A written status report on a fixed day. It says where the work is, what is left, what is happening this week, and which issues, risks and questions are open. Ours goes out every week and covers those four things.
- Budget spent beside work accepted. Put the two numbers next to each other. If half the budget is gone and a quarter of the work has been accepted, that is a conversation for this week, while there is still room to change the plan.
- Working software, shown to you. A demonstration of something that runs tells you more than a percentage on a slide.
- Bad news that reaches you from the vendor first. If you learn about a slipped date by asking, or from your own users, write that down. How early you hear about a problem is the most useful single measure of the vendor.
- Open risks and decisions, each with a name and a date. The list includes the ones that are waiting on your side.
- Changes agreed before they are built. Every change to the scope has a cost and an approval on record before work on it begins.
- Commits arriving in your repository. You do not have to read the code. You are checking that it arrives steadily and that a second engineer reviews it.
- Changes to the team, announced in advance. People move on any long engagement. You should hear about a change before it happens, with a plan for handing over what the person knew.
Jim Wissing, the president of Express Freight Handlers, describes this routine in his review on Clutch. During the main build of his company’s system there was a call every Wednesday to go over what had been done the week before, the problems that had come up and the business questions that needed an answer. When a deadline was going to be missed, he writes, our team called him to explain the reason.
What to check at each release and at the end
- Acceptance against the written result. The person named before the work started tries the release on real work, and either signs off or lists what is missing.
- A deployment someone else could repeat. The steps are written down, and someone on your team has watched one or done one.
- Documentation a second person has followed. A document that nobody has worked from has not been tested.
- Access in your company’s name. Administrator accounts, cloud subscriptions, domains, keys and certificates are registered to the company, and at least two of your people can get in.
- Support after launch, agreed before launch. You know who is called, how quickly they respond, and what it costs.
What to do when an item fails
Treat one missed item as information. Raise it in writing in the week it happens, with the named person, and ask for the cause and a date. Most problems end there. A vendor that answers plainly has also shown you how it behaves under pressure, and that is useful to know early.
A pattern needs a different response. If the same item fails again after a date was agreed, take it to the vendor’s leadership once, with the record. If the explanation is one you cannot check, get an independent opinion of the work before you decide anything. Software Project Rescue: The Warning Signs and the First 30 Days describes the signs that a project is in trouble and what a rescue does in its first month.
What the vendor can fairly expect from you
Accountability runs in both directions. A vendor can be held to a date only if your side made its decisions on time, gave access when it was asked for, and reviewed what was delivered. Keep the same record for your side that you keep for the vendor: what was asked of you, when, and when you answered.
The Client’s Job on a Software Project lists what a project needs from the client and how many hours a week it takes.
Common questions
Can a contract make a vendor accountable on its own? No. A contract tells you what you can do after something has gone wrong. What keeps the work on track is a named person on each side and a weekly look at progress, budget and open risks.
How often should we review the work with the vendor? Every week while something is being built or changed. A recurring service that is running steadily can move to a monthly review against the service levels in its agreement.
What if the vendor says the delay is on our side? Sometimes it is. Check the record of what the vendor asked for, when it asked, and when your side answered. If your decisions or access were late, fix that first. If nothing was written down, start writing it down this week.
When is it time to replace the vendor? When the same item fails again after you raised it in writing and a date was agreed, and the explanation is one you cannot check. Get an independent opinion of the work before you decide, so the next firm starts from facts.
Does the checklist apply to an MSP agreement? The items on ownership, the named person and how the agreement ends apply unchanged. The weekly list becomes a monthly review of the service levels, the open tickets and the changes made to your environment.
If you cannot tell from the inside whether a vendor’s work is sound, a System Evaluation gives you an independent written account of the system for a fixed fee.