Read a proposal in a set order: the result it commits to, what the estimate is made of, what it assumes, what it leaves out, and what happens when something changes. A proposal is a good one when you can say why the number is what it is and what would make it move. Leave the price for last, because two prices can be compared only when you know they are for the same work.
Start with the result the proposal commits to
Look first for your own problem, in your own terms. A proposal that repeats your request as a list of features tells you what the vendor will build. It does not yet tell you whether the vendor understood why you asked. Check for four things.
- The outcome, written so that you could tell afterward whether it happened.
- The deliverables, each with a description of what it does when it is finished.
- The person on your side who accepts each deliverable, and how.
- What the first release contains, and what is left for later.
A proposal that moves part of your request to a later phase and explains why deserves a careful read. The vendor has usually thought about which parts of the request produce the result you named.
Find out what the estimate is made of
A single number tells you very little, so ask what it is built from.
- What it is based on. Find out whether someone looked at the actual system, the data and the integrations, or only at the document you sent. An estimate made only from your document cannot allow for what the document leaves out.
- How it breaks down. The estimate should be divided by part of the work, with the largest items visible. Ask the vendor which items are largest and what would make each one larger.
- Which work is inside the hours. Design, testing, project management, deployment, data migration and documentation take a real share of any project. A low number often leaves some of them out.
- Whether it is a range. Early in a project, a range is the honest form of an estimate. Ask what would put the work at the bottom of the range and what would put it at the top.
- Which kind of contract it assumes. A fixed price, a fixed budget and hourly billing put the risk in different places. Fixed budget, fixed price, or hourly explains each one.
Read the assumptions as conditions on the price
Every assumption is a condition. If it turns out to be false, the price or the date changes, and the contract usually says at whose cost. For each assumption, ask who will check it, when, and what happens to the number if it is wrong.
Assumptions tend to fall into four groups.
- About your side. Decisions within a set number of days, people available for a set number of hours a week, access provided by a date. Check that you can keep these, because you are agreeing to them.
- About other systems. The ERP has a usable API, the other vendor will cooperate, a test environment exists.
- About the data. It is in one place, it is reasonably clean, and there is about as much of it as the vendor was told.
- About what already exists. The documentation is current, and the code the last team left can be built on.
General assumptions, such as “the client will provide timely feedback”, appear in every proposal and tell you little. Assumptions that could only have been written about your project show that the vendor has thought about it.
A proposal with no assumptions still has them. They are unwritten, and you will meet them later as change requests.
Look for what is missing
What a proposal leaves out is harder to see than what it gets wrong. Go down this list. For each item, find the sentence that covers it, or ask.
- Moving the data from the old system, including cleaning it.
- Each integration, by name, with who builds each side of it.
- Environments, deployment, hosting and licenses, and who pays for the third-party costs.
- Testing, including what your own people are expected to do before they accept a release.
- Security and access: roles, sign-in, an audit trail, and anything a compliance requirement adds.
- Training and the rollout to users.
- Documentation and handover.
- Support after launch, and what it costs.
- Who owns the code, and when ownership passes to you.
- The people: their names and roles, where they are, and whether any of the work is passed to another company.
- Retiring the old system.
It is fine for an item to be out of scope. It should be out of scope in writing, so that you can put it in your budget somewhere else.
Check how the proposal handles change
Something will turn out differently from the plan, and the proposal should say what happens then.
- How a change is raised, priced and approved, and who on each side can approve it.
- Who pays when a piece of work takes longer than estimated.
- How you will see the budget spent beside the work finished, and how often.
- Whether payments are tied to dates or to milestones you have accepted.
- How either side can end the engagement, and what is handed over.
The contract terms themselves are for your counsel to read. Your part is to make sure the proposal answers these questions before the contract is drafted from it.
Put the proposals side by side, and compare price last
Make one page with a column for each vendor and a row for each of the points above: the result, the basis of the estimate, the assumptions, the exclusions and the handling of change.
When one price is far below the others, the usual reason is a difference in scope or in assumptions. Find that difference before you treat the lower price as a saving. Ask the lowest bidder what it left out, and ask the highest what it added.
A Sample Software RFP Response, Walked Through sets an invented weak response beside a strong one, section by section.
When the scope is not defined yet
Sometimes the proposals disagree widely because nobody has defined the work. More proposals will not fix that. The useful purchase is a small planning step with a fixed fee, which ends with a scope, written requirements and a number. You own what it produces and can give it to any vendor.
That is the order we work in: a ballpark range after the first conversations, and a fixed proposal only after a planning step.
Common questions
Why is one proposal so much cheaper than the others? Usually because it covers less or assumes more. Compare the scope, the assumptions and the exclusions line by line before you compare the price. If they match and the price is still far lower, ask the vendor how it gets there.
Should a proposal give a fixed price or a range? It depends on how well the scope is known. A fixed price fits work that is small and well defined. For work nobody has designed yet, a range with the reasons it could move is more honest than a single number.
Is it reasonable to pay for a planning step before the proposal? Yes, when the scope is not yet defined. Check that the step has a fixed fee and that what it produces belongs to you, so that you can take it to another vendor.
Who should read the proposal besides IT? The person in the business who owns the process should read the result and the assumptions about their team. Finance should read the payment schedule, and counsel should read the contract terms.
If the proposals in front of you disagree because the scope was never defined, a VDP Sprint produces mockups of the key screens, written requirements and a roadmap with the investment for a fixed fee, from $9,500, and the result is yours to take to any firm.