How do you take in and rank IT project requests? An intake and prioritization worksheet

Take every project request in on the same form, put the work with a real date first, score the rest on the same three questions, and rank the list against the hours your team has. The worksheet is on this page.

Take every project request in on the same one-page form, put the work with a real date first, score the rest on the same three questions, and rank the list against the hours your team really has for projects. The worksheet below has those parts: the request form, the scoring questions, the hours available and the ranked list you take to whoever decides. Copy the tables into a spreadsheet or a shared document.

It is for projects. Support tickets and small changes that IT can decide alone do not need it.

The request form

The person asking fills in the first half.

Field What to write
Request A short name for it.
Asked by Name and department.
Sponsor The person who answers for the result and can commit the department’s time.
The problem Two or three sentences on what happens today. Describe the problem and leave the solution out.
Who is affected Which people or customers, and how often.
What it costs today Hours a week, errors, lost orders or a risk. Give a count if you have one.
If nothing changes for a year What gets worse, and for whom.
Date Any deadline, and what sets it: a contract, a regulator, a vendor ending support, a business event.
Already tried Workarounds in use, and tools already looked at.
People from the department Who will answer questions and test, and how many hours a week each.

IT fills in the second half, with the sponsor.

Field What to write
Kind of request A project, a small change, or something that is not IT work. Only projects go on.
Systems and data Which systems it touches, and which data.
Options A system you already own, a product to buy, something to build, or a change to the process.
Size How much of the team it takes, scored from 1 to 3 on the scale below, and which people it needs.
Cost to run What it costs after go-live, and who supports it.
Depends on Other projects, a vendor, a data cleanup, or a decision somebody has not made.
Risks What could make it larger or later.

For the options line, Build vs. Buy Software Analysis for Growing Companies goes through when buying is the right call and when it is not.

Work that has a real date

Some work is not a choice: a product leaves support on a published date, an auditor or an insurer has set a deadline, or a contract commits the company to something. It is not scored. It goes at the top of the ranked list with its date, and its hours come out of the team’s time first.

Check that each date is real: a date someone offered in a meeting is a preference, and that request is scored with the rest.

The scoring questions

Score every other project from 1 to 3 on three questions. The three scores stay separate, and there is no total.

Question 1 2 3
What is it worth? It removes an inconvenience for a few people It ends regular lost hours or rework in one department It protects or brings in revenue, ends errors a customer sees, or keeps work from stopping
What happens if it waits a year? Nothing changes The cost grows, or the workaround gets harder to keep up The work gets much more expensive or more dangerous the longer it sits
How much of the team does it take, and which people? Under a month of work for one or two people, in one system One to three months, or more than one system Longer than a quarter, a new system, or a change to how more than one department works

The third score is the project’s size. Write beside it the names of the people the project needs, because a project that needs your scarcest person for three months costs more than its hours suggest. Give a project that scores 3 on size a design step before anyone commits to a number.

A fourth question, what the project depends on, is answered in words. The answer is already on the second half of the form.

The hours available

Fill this in from the last three months of actual work, not from the plan.

Line Hours this quarter
Hours the team works in total
Less support and keeping systems running
Less small changes
Less IT’s own required work: security fixes, upgrades, recovery tests
Less work with a real date
Left for projects

The ranked list

Rank Project Sponsor Worth (1 to 3) If it waits a year (1 to 3) Size (1 to 3) Depends on Decision Decided by, and date Next review
Dated Not scored Not scored
Reserved Required work Not scored Not scored
1
2
3

In the decision column write: start now, next, waiting, handled another way, or declined. For a project that is waiting or declined, add what would change the answer. For dated work, write its date and its latest safe start.

How to rank the list

  1. Below the dated work, put the projects that are worth the most and that lose the most by waiting a year.
  2. Where two projects are about level on those two scores, put the smaller one first. It delivers sooner and ties up fewer people.
  3. Move a project up when others depend on it, and write the reason beside it.
  4. Put a rough number of hours on each scored project from its size, and go down the list adding them up until the hours left for projects are used. Draw a line there. What is above the line is started or next. What is below it is waiting.
  5. Take the list, with the line on it, to the executive team or the steering committee. They may change the order. When they do, something moves below the line, and the reason goes on the list.

The scores exist so that every request is discussed in the same terms. They do not make the decision. When a score is disputed, the dispute is usually about a fact, such as the hours lost each week, and a fact can be checked.

A project with no sponsor, or with nobody from the department named and freed to test, tends to stall whatever it is worth. Are You Ready to Start Your Custom Software Project? covers what to settle before a project starts, including who is committed to it.

How to keep the list in use

Keep one list, and let anyone in the company read it. Review it on a set date, for example once a quarter, and whenever a project above the line finishes or stops. Score a request again when a fact changes. Update the hours each quarter from actual work, because that number moves more than people expect.

Common questions

Who fills in the request form? The person asking fills in the first half, and names a sponsor who can commit the department’s time. IT fills in the second half. If the problem line names a product, talk to the person before going further.

Why is there no total, and no weighting? Totals and weights look exact and are hard to defend. Three questions scored from 1 to 3 are enough to put requests in rough order and to show where two people disagree about a fact. People still make the decision.

Where does the work go that IT has to do and nobody asked for? Put it on the same list, where everyone can see it, and do not score it line by line against the projects. Security fixes, upgrades and recovery tests take a reserved share of the team’s hours, agreed once with the executives, and are not ranked against a department’s request. An upgrade before a vendor ends support has a real date and goes at the top.

How often should a request be scored again? When a fact changes, and at each review of the list. A request that is waiting because nobody was named to test can move up on the day its sponsor names people and frees their time.

If a project near the top of the list is a system to build, and it is too large to size from a form, a VDP Sprint is the fixed-fee first step: it ends with requirements, a technology recommendation and a roadmap with the investment.