Write down the short list of decisions that belong to the committee, seat the people who can commit money and staff, and bring every item as a choice with its cost. A committee stops deciding when its meetings fill up with status reports, when the members who can say yes send deputies, or when nobody recorded what was agreed last time. A one-page charter, an agenda made of decisions and a log of what was agreed deal with each of those.
1. Write down what the committee decides
A committee with no stated job will take up whatever is put in front of it, and that is usually a project update. Put its decisions on one page.
- The order of the projects that cross departments or need new money.
- What is stopped or moved back to make room for something new.
- A change to an approved project’s scope, budget or date beyond a set amount.
- The share of IT’s time reserved for support, security work and upgrades.
- A risk that IT has raised and the business chooses not to fund. The committee accepts it by name.
On the same page, list what stays with IT: the technical design, the choice of tools inside an approved budget, the daily order of support work, small changes, and emergency fixes. Listing both keeps technical choices out of the meeting, and keeps the order of the projects from being left to IT alone.
2. Seat the people who can commit money and staff
A decision holds only when the people who made it control what it needs. That means the heads of the departments that use most of IT’s project time, whoever holds the budget, and the IT leader. Keep the group small enough that everyone speaks, which usually means fewer than eight.
The chair should be the executive who can settle a disagreement between two department heads. In most mid-market companies that is the CEO or the COO. The IT leader prepares the agenda, brings the recommendations and runs the discussion, and should not be the chair. When IT chairs, the order of the projects is treated as IT’s opinion, and the departments go on arguing about it outside the room.
Do not accept a deputy who has to go back and ask. A member who cannot attend sends a decision on each item in writing.
3. Build the agenda from decisions
Write each agenda item as a question the committee can answer in the meeting. “Do we start the warehouse project this quarter and move the CRM upgrade to the next, or the reverse?” can be decided in the meeting, and “Warehouse project update” cannot.
Each item comes with a one-page brief, sent at least three working days ahead.
- The decision requested, in one sentence.
- The options, including doing nothing.
- What each option costs in money and in the team’s time.
- What each option would move back.
- IT’s recommendation and the reason for it.
- The sponsor in the business who is asking.
An item with no brief waits for the next meeting. Status goes into a written report that members read beforehand, and the meeting discusses only the exceptions: a project whose date, cost or scope has moved past the amount in the charter.
4. Show how much the team can take on beside the list
The committee cannot set an order without knowing how much fits. Bring one page to every meeting: the projects in ranked order, the size of each, the hours the team has for projects this quarter after support and its own required work, and a line drawn where those hours run out.
Then hold to one rule. Nothing moves above the line unless something else moves below it, and the committee names which. Without this rule, approving a project costs the committee nothing, so everything is approved and the order is never settled.
5. Agree how a decision is made, and record it
Aim for agreement. Where there is none, the chair decides before the meeting ends. If a decision has to wait, record what information is missing, who will bring it, and the date.
Keep a decision log with five columns: the date, the decision, the reason, who owns the next step, and when it is due. Send it to the members within a day. Open the next meeting with it, and spend five minutes on what was decided last time and whether it happened, because decisions that nobody checks on tend not to be carried out.
6. Meet as often as there are decisions to make
An hour a month is a reasonable place to start for a mid-market company with several projects under way. Add a longer session once a quarter to rank the whole list again against the business plan.
If a meeting has no decision on its agenda, cancel it and send the status report. Members keep attending a meeting that is only held when it is needed.
Some decisions cannot wait a month. Say in the charter who may make one between meetings, for example the chair with the IT leader and the sponsor concerned, and have them report it at the next meeting so that it goes in the log.
7. Deal with decisions that are made outside the room
Sooner or later someone takes a request straight to the CEO. Ask for it to come to the committee, or for the CEO to decide it with the displaced project in view. Either way, record it in the log like any other decision.
If it happens often, the cause is usually the committee. It may meet too rarely for the pace of the business, or it may be spending its time on decisions nobody is waiting for.
When a committee is more than you need
If one executive sets every priority and IT has a handful of projects, an hour a month with that executive and the same one-page list does the same job. Start a committee when projects from different departments begin to compete for the same people.
Before you set up a second committee for AI or for data, try giving those decisions to this one, since the same people would usually sit on both.
Common questions
Who should chair an IT steering committee? The executive who can settle a disagreement between two department heads. In most mid-market companies that is the CEO or the COO. The IT leader prepares the agenda and makes the recommendations.
How often should it meet? Monthly is a good place to start, with a longer session once a quarter to rank the whole list again. If a meeting has no decision on its agenda, cancel it and send the status report.
What if the committee keeps putting decisions off? Ask what was missing each time. If it was information, the brief needs more in it. If it was the person with the authority, change the membership or have that person send a decision in writing.
Should our MSP or software partner attend? For the items that concern their work, yes, as a guest. They can speak to size, risk and timing. The decisions stay with the company’s own people.
How is this different from a steering committee for one project? A project steering committee oversees one project and ends when the project does. This one ranks all the projects against each other, and it stays in place.
If you want a senior technologist beside you in those meetings, a fractional CIO/CTO through Strategic IT Advisory is a named person on a monthly retainer, with a cadence that includes your leadership meetings.