Decide what moves, give each set of data an owner in the business, clean it in the old system, load it with a script you can run again, and prove the load by reconciling totals between the two systems.

Decide what data moves, give each set of data an owner in the business, clean it in the old system, and load it into the new one with a script you can run again. Then prove the load by reconciling totals between the two systems, and have each owner sign off. Start when the project starts, because the cleaning is done by people who also have their regular work.

If you are moving off Dynamics GP, you know how long you have. Microsoft’s lifecycle page for Dynamics GP says support for product enhancements, regulatory (tax) updates and technical support ends on December 31, 2029, and that security updates will be available, if needed, until April 30, 2031.

1. Decide what moves and what stays behind

Every record you move has to be mapped, cleaned and reconciled, so the first job is to move less. Sort the data into three kinds.

  • Master data: customers, vendors, items, the chart of accounts, employees. The active records move. A customer with no activity in years, or an item that was discontinued, can stay behind.
  • Open transactions and balances: open sales orders and purchase orders, unpaid invoices on both sides, inventory on hand, general ledger balances. These have to move, and they have to be right.
  • Closed history: paid invoices, shipped orders, old journal entries. Moving it is a choice. Bring a limited period, and keep the old system available to read for the rest.

Ask finance and your auditors what they need from the old records before you settle the third one.

2. Give each set of data an owner in the business

IT cannot decide which of two customer records is the correct one. Someone in the business can. Name one owner for each set: receivables or sales for customers, purchasing or payables for vendors, operations for items, the controller for the chart of accounts and the balances.

The owner decides the rules: what counts as a duplicate, which record survives, what is inactive. The owner also signs the reconciliation in step 6. Confirm in the statement of work who does which part. An implementation partner’s scope usually covers loading the data, and deciding what is correct stays with the company.

3. Measure the data before anyone cleans it

A profile of the data gives you a list of problems with a count beside each one, which is something you can assign and schedule. For each set of data, count these.

  • Records in total, and how many are active.
  • Likely duplicates: the same tax ID, the same address, names that differ by punctuation.
  • Required fields that are blank.
  • Values that will not fit the new system, such as free text where it expects a choice from a list, or units of measure and payment terms that have no equivalent.
  • Records that point at something missing, such as an order for a customer that was deleted.
  • Open transactions that are dead, such as a purchase order from years ago that was never closed.

Give each owner their list, with the counts, and agree on a date for each item.

4. Clean the data in the old system

Fix the records where they live: merge the duplicates, close the dead purchase orders, fill in the blanks. There are two reasons to do it there. The old system keeps running until cutover, so a correction made only in a spreadsheet is lost at the next extract. And the people who enter the data keep working in the old system, so they will keep making the same errors unless something changes.

Change how new records are created at the same time. A required field or a short written rule stops new bad data from arriving while you clean the old.

Some fixes cannot be made in the old system, because the new one is structured differently. Write those as rules in the load script. A fix made by hand in a file has to be made again by hand on every load.

5. Make the load repeatable

Build the extract, the transformation and the load as scripts, with a mapping document that lists each old field, the new field it goes to and the rule applied. Then run the whole load into a test copy of the new system more than once.

Each trial load finds problems, and it is far better to find them in a test. It also tells you how long the real load will take, which sets the length of the cutover.

Keep a table that matches every old ID to its new one. Integrations and reports need it during the move, and people need it for years afterward, when a customer calls about an invoice with an old number.

6. Reconcile totals first, then individual records

Reconciliation is the proof that what arrived is what left. Do it at three levels on every trial load and on the final one.

  1. Counts. The records extracted equal the records loaded plus the records rejected, and every rejected record has an explanation.
  2. Totals. The same report, run in both systems as of the same date, gives the same number.
  3. Records. Each owner picks a sample that includes the awkward cases, such as the largest customer, a customer with a credit balance and an item stocked in several locations, and compares them screen to screen.
What to compare Old system and new system must agree on
Receivables Total open amount, and the amount by customer
Payables Total open amount, and the amount by vendor
Inventory Quantity and value, by item and by location
General ledger The trial balance, account by account
Open orders Number and value of open sales orders and purchase orders

Check inside the new system as well: the receivables total should equal the receivables account in the general ledger, and the same for payables and inventory. A difference is either corrected or explained in writing, and the owner signs. Matching counts are not enough. The right number of invoices can still carry the wrong amounts.

7. Plan the cutover around a freeze

Set a cutoff date. From that date, stop changes to master data in the old system, run the final extract, load it, and run the same reconciliation reports one last time. Agree on the conditions for going live before that day, so the decision does not depend on how tired everyone is. A plain condition works: if the totals do not match, the go-live moves.

Keep the old system available to read after go-live. Then reconcile the opening balances again at the first month-end close in the new system, which is the first full test of the data.

The systems connected to the ERP

The CRM, the warehouse system, the e-commerce site and the reporting database all hold the old customer and item IDs. Each one needs the table of old and new IDs, and its own place in the cutover plan. List them at the start, because this work is easy to leave out of the scope.

Common questions

How much history should we migrate? As little as the business can work with. Master data, open transactions and balances have to move. For closed history, bring a limited period and keep the old system available to read. Ask finance and your auditors what they need from the old records before you decide.

Who is responsible for cleaning the data, IT or the business? Both, for different parts. The business owner of each set of data decides what is correct and signs the reconciliation. IT profiles the data, builds the extract and the load, and runs the comparisons.

Should we clean the data before the migration or after it? Before, and in the old system wherever you can. Bad data is harder to fix once it is in the new ERP, because new transactions attach to it from the first day.

How many trial loads do we need? Enough that the last one ends with nothing unexplained. Plan for at least two full trial loads before the real one, and expect each of them to find problems.

If the new ERP has to exchange data with systems that are staying, Integrations & APIs covers that work, and it starts with a fixed-fee System Evaluation.

Related service: Integrations & APIs

More like this, in your inbox. Subscribe for our latest thinking, resources, and events.