How long does an ERP integration take, and what does it cost?

Our published range for connecting several systems and reporting on the data is 8–20 weeks and $15k–$250k. One integration is a smaller job, and a handful of things decide where yours lands.

Budget in months: our published range for integration work, connecting several systems and reporting on the data, is 8–20 weeks and $15k–$250k, and that covers a set of integrations with a reporting layer on top. A single integration between two systems is a smaller job in the same range. A focused, well-scoped integration between two platforms can go live in 60–90 days, the range our guide Best system integration companies for mid-market operators gives. Where the price lands in the range depends on how the ERP lets you connect, how clean the data is, and how much has to happen when a record fails.

The published figures that apply

These are from our pricing page.

Work Typical schedule Published price
System Evaluation: systems, integrations and data flows mapped, with a prioritized plan and a fixed proposal 1–4 weeks Fixed fee, from $3,500
Connecting your systems and reporting on the data 8–20 weeks $15k–$250k
A small dedicated team for continuous work Ongoing From $25,000 per month
Time and materials, with a monthly cap As needed $100–$300 per hour, by role
Support after go-live Ongoing Reserved hours, sized to the system and billed monthly

Three costs are missing from the table because they are not ours to quote: any ERP license or API add-on the integration needs, the subscription for an integration platform if you use one, and your ERP partner’s time. Get each of them in writing from the vendor or the partner before you set the budget.

One integration is usually several data flows

“Connect the ERP to the CRM” sounds like one integration. In practice it is customers in one direction, items and prices in the other, orders in, invoices and payments back, and inventory on a schedule. Each of those is a data flow with its own direction, timing, owner and ways of failing.

An estimate is built flow by flow. List the flows before you ask anyone for a number, and you will get a number you can compare.

What moves the schedule and the cost

These are in rough order of how much they matter.

  • How the ERP lets you connect. A documented API with a sandbox is the short end. File drops, a database you may read and not write, or an old version with no supported interface is the long end. The older and less documented the system, the more work each connection takes.
  • The state of the data. If customers do not share an ID across the two systems, matching them is part of the project. This is usually where the cost hides.
  • Direction and timing. One way, once a night, is the simplest case. Two ways, within seconds, with both systems allowed to change the same record, is the most work. Ask the business what delay it can live with before you assume real time.
  • What happens when a record fails. Validation, retries, a queue that a person works, an alert, and a way to rerun a day. This can be as much work as the path where everything goes right, and it decides what the integration costs to own.
  • Proof that the systems agree. Finance will ask for a report that reconciles the two sides. Build it as part of the integration.
  • Other people’s calendars. Sandbox access, credentials, the ERP partner’s change window and the other vendor’s support queue are schedule you do not control. Start those requests first.
  • Whether the ERP is about to change. If a migration is planned, keep the part that talks to the ERP separate so it can be rewritten alone, or wait.

Where the time goes

The work has five stages: agreeing the flows and which system owns each field, building, testing with a copy of real data, running beside the manual process until the numbers reconcile, and switching over.

The build is often not the longest stage. The agreement at the start and the reconciliation at the end depend on finance and operations people who have other work, and they take as long as those people’s calendars allow. How long does custom software take to build? covers what drives a schedule in general.

What the large end looks like

At the large end, the job is connecting a dozen or more systems. One of our clients shows what that involves.

Legends Global ran 15 business-critical systems that never talked to each other. We built the integration hub that connected them, which cut month-end close from five days to one. The case study describes the hub.

What it costs after go-live

An integration is software, and it needs an owner. An API changes, the ERP is upgraded, someone adds a field. Budget for support as reserved hours, sized to the system and billed monthly, and for hosting at cloud cost plus a monthly management fee if we host it. Budgeting for software maintenance goes through the lines to plan for.

How to start small

  1. List the flows and rank them. Rank by the hours of re-keying each one removes or the errors it causes today.
  2. Get the systems mapped. A System Evaluation takes 1–4 weeks for a fixed fee from $3,500, and it ends with a prioritized plan and a fixed proposal for the first integrations.
  3. Build one flow end to end. Include the failure handling and the reconciliation report. The first flow costs the most, because it carries the access, the environments, the monitoring and the deployment that every later flow reuses.
  4. Price the rest from the first. After one flow is live, the estimate for the others rests on what was learned.

Where the scope is clear, the price can be fixed. Fixed budget, fixed price, or hourly explains which model fits which kind of work, and How much does custom software cost in 2026? has the ranges for every other kind of project.

Common questions

What does a single integration cost? It falls in our published range for connecting your systems and reporting on the data, $15k–$250k over 8–20 weeks. Two integrations with the same name can be very different jobs, depending on how the ERP can be reached, the state of the data and what has to happen when a record fails. A System Evaluation ends with a fixed proposal for the first ones.

Is an integration platform cheaper than custom code? It depends on how many integrations you will run and who will maintain them. A platform adds a subscription and saves building the same plumbing each time. For a handful of integrations, custom code can cost less to own. Get the subscription price from the vendor in writing.

Can the price be fixed? Yes, when the scope is clear. A defined integration with access already in place can be fixed price and fixed scope. A larger set is usually a fixed budget with controlled scope, where the budget holds and the scope flexes.

What does an integration cost to run after it goes live? Plan for support hours and hosting. We price support as reserved hours sized to the system and billed monthly. How many hours depends on how often the systems at either end change.

How do we shorten the schedule? Ask for sandbox access and credentials on the first day, name one person who decides which system owns each field, and cut the first release to the data flows that remove the most re-keying.

Our Integrations & APIs work starts with a System Evaluation, which maps the systems and the data flows and ends with a fixed proposal for the first integrations.