What does a data and reporting project cost?

A dashboard or a set of reports on data you already have runs $15k–$95k. Connecting several systems and reporting on the result runs $15k–$250k. Here is what moves the number.

One dashboard or a set of reports on data you already have costs $15k–$95k and takes 4 to 10 weeks. Connecting several systems, agreeing on one definition for each number and reporting on the result costs $15k–$250k and takes 8 to 20 weeks. Those are our published ranges, the same ones on our pricing page, and where a project lands depends mostly on how many systems are involved and what state the data is in.

The ranges, by kind of project

Kind of project Typical schedule Typical budget
A dashboard or report from data you already have 4–10 weeks $15k–$95k
Connecting your systems and reporting on the data 8–20 weeks $15k–$250k
A system with heavy security or compliance requirements 24–52 weeks $320k–$1.5M+

The first row is one dashboard or a set of reports on top of data you already collect in a spreadsheet, a CRM, an accounting system or a database. The data is connected, cleaned up and put in front of the people who need it, with the numbers agreed on first.

The second row is the larger job. The systems that do not talk to each other are connected, each number gets one definition, and dashboards and alerts go on top.

The third row applies when the data platform is itself something an auditor or a regulator will review, such as anti-money-laundering or financial reporting. Access controls, audit trails and the evidence an examiner asks for are a real share of that budget, so they are planned at the start.

A data warehouse is not a separate line on the list. A warehouse project falls in the second row, connecting your systems and reporting on the data, at $15k–$250k over 8 to 20 weeks. Often the first and biggest gain comes from integration and a governed layer with one definition for each number. A warehouse comes later if the volume of data or the questions call for one, and it adds to the work when it does.

What moves the number

These are roughly in the order they matter.

  • How many systems there are, and how hard each one is to read. A system with a documented API is quick to connect. An old system that can only export files takes longer, and so does one whose vendor controls access to the data.
  • The state of the data. If the data is fragmented or wrong, fixing it is part of the project. Duplicate customers, missing keys and free-text fields that should have been codes are where the cost usually hides.
  • How many definitions have to be agreed. If three departments report three revenue numbers, someone has to get them to settle on one. That takes meetings with people who have other jobs, and it adds calendar time more than engineering time.
  • How much history is needed. Loading this year from one system is simple. Loading five years across a system that was replaced along the way means reading the old system’s data too.
  • How fresh the numbers have to be. A nightly load is simpler to build and to run than one that updates within minutes. Ask which decision needs the faster number before you pay for it.
  • Who will see it. Rules about which region, customer or cost center each person may see add work, and so do users outside the company.
  • How much is already decided. A plan that has been checked against the real systems narrows the range.

What a larger project looks like

One client project shows what the scope looks like when many systems are involved. For K2 Integrity, 12 fragmented source systems were consolidated into one audited data warehouse for anti-money-laundering work, and detection was rebuilt on top of it. The firm passed its next regulatory examination with zero findings. Its case study describes the work.

What it costs to run afterwards

Three costs continue after the first release.

  • Hosting. If we host it, you pay the cloud costs at pass-through and a fixed monthly management fee: $250–$750 per month for lightweight tools and test environments, $750–$2,500 per month for basic business applications in production, and $2,500+ per month for advanced applications with high activity or compliance requirements.
  • Maintenance and support. This is priced as reserved hours, billed monthly and sized to the system: around 100 hours a year for a stable system with occasional fixes, around 200 for one that gets regular minor enhancements, and around 400 for one the business changes often.
  • Licenses. A reporting tool and a data platform are licensed from their vendors, and those prices are theirs. Read the current price list before you choose a design, because the license model can decide which design is cheaper to run.

If the data work is continuous and not a single project, a small dedicated team starts at $25,000 per month.

How to keep the first project small

Pick the report the business argues about most, and build that one properly from the source systems to the screen. That first piece shows how hard your data is to work with, and that tells you more about the cost of everything after it than any estimate made beforehand.

Phasing the work this way also keeps the money in step with what you have learned. When the planning step has produced a scope we both believe in, we fix the price. Where the work is still taking shape, we work to a fixed budget with controlled scope. Fixed budget, fixed price, or hourly explains who carries the risk under each, and How much does custom software cost in 2026? has the ranges for every other kind of project.

Common questions

Do we need a data warehouse, and does it change the price? Sometimes. Often the first and biggest gain comes from connecting the systems and agreeing on one definition for each number. A warehouse comes later if the volume of data or the questions call for one, and it adds to the work when it does.

Why is the range for one dashboard so wide? Because the dashboard is the small part. If the data sits in one clean system, the work is short. If it has to be pulled from several places and corrected first, most of the budget goes there.

Can the price be fixed before we start? Yes, once the scope is defined. A System Evaluation ends with a fixed proposal for the first piece of work. Larger projects are broken into milestones, each with its own fixed fee.

A System Evaluation, a fixed fee from $3,500, maps your systems and data flows and ends with a fixed proposal for the first piece of work.