Ask the people who run each part of the business two things about each system they depend on: how long they could work without it before it costs money or a customer, and how much recent work they could afford to enter again. The first answer becomes the recovery time objective (RTO) and the second becomes the recovery point objective (RPO). Then work out what it costs to meet each answer, show them the price, and let them choose. The objective is the figure they choose and fund, written down and tested.
What RTO and RPO mean
Both terms are defined in the glossary of the National Institute of Standards and Technology (NIST), which takes them from its Special Publication 800-34.
- Recovery time objective (RTO). NIST defines it as the overall length of time a system’s components can be in the recovery phase before the delay harms the organization’s mission or business processes. In plain terms, it is how long until the system is back.
- Recovery point objective (RPO). NIST defines it as the point in time to which data must be recovered after an outage. In plain terms, it is how much recent work you can lose, measured as time back from the failure.
An example shows the difference. A system is backed up every night at midnight and fails at four in the afternoon. Restoring it takes six hours. When it returns, everything entered since midnight is gone, which is sixteen hours of work. That system meets an RPO of one day and misses an RPO of one hour, however fast the restore is.
Why IT should not set the numbers alone
IT knows what a recovery costs, and the business knows what an outage costs. When IT picks the figure alone, the company either pays for more protection than it needs or finds out during an outage that the head of operations never agreed to a day without the warehouse system.
Asking the business with no price attached does not work either. Every department will say its system can never be down, because that answer costs nothing to give.
Start with the systems that would stop the business
You do not need an objective for every system this quarter. List the systems where an outage stops orders, billing, payroll, production or service to customers, and start there. Which of your systems and processes depend on one person? has a list that helps you find them.
Put the systems into three or four tiers, each with one RTO and one RPO. A few tiers are easier to explain and to test than forty separate figures.
What to ask the people who depend on the system
The person who owns a process usually cannot give you an RTO. They can tell you what happens to their day. Ask these questions and write the answers down in their words.
- What stops when the system is down? Ask what carries on as well: paper tickets, the phone, a spreadsheet.
- How long can the workaround last? An hour on paper is an inconvenience. A week on paper may be impossible.
- When does it start to cost money or a customer? Ask for the point: after an hour, a shift or a day.
- Is there a time when the answer changes? Month-end close, payroll day and the busy season often need a tighter figure than an ordinary Tuesday.
- If the system came back as it was last night, how would today’s work get back in? From paper, from email, from another system, or not at all.
- Is there anything that could not be entered again? Orders taken by phone, signatures and readings from equipment are examples.
The first four answers give you the recovery time. The last two give you the recovery point.
Put a price beside each answer
Now do IT’s half. For each tier, work out what it takes to meet the figure the business asked for, and put one cheaper option beside it.
| What the business asks for | What it usually takes |
|---|---|
| Back within a few days, losing up to a day of work | Nightly backups kept away from the system, a written procedure for rebuilding it, and a restore that has been tested |
| Back within a few hours, losing up to an hour of work | Backups or copies of the database log taken through the day, a standby environment that can be started, and people who have practiced the procedure |
| Back within minutes, losing almost nothing | A second running copy kept in step with the first, automatic detection and switchover, and someone on call at all hours |
Each row costs more than the one above it, in infrastructure and in people’s time. Take the options and their costs to the owner of the process and to whoever holds the budget. A request for no downtime at all often becomes a request for the middle row once the price is on the table.
Count the whole outage
Recovery time runs from the moment the system fails, and the restore is only one part of it. Add the time to notice, the time to reach the person who can act, the time to decide between waiting and restoring, the restore itself and the checks afterwards.
Noticing can be the longest part. Dave & Buster’s and Main Event had been finding out about outages when guests complained. They went to catching 95% of issues before anyone was affected. The case study describes the work.
Check dependencies as well. A system cannot come back faster than the things it needs: sign-in, the network, the database server, the integration that feeds it. If the order system is promised in two hours and the directory it signs in against is promised in eight, the real figure is eight.
Write the objectives down and test them
Record one line for each system: the owner in the business, the RTO, the RPO, how each is met, the date of the last test and what the test showed. Have the owner and the budget holder sign it.
An objective that has never been tested is an estimate. Restore the system to a test environment, time it from start to finish, and compare the result with the figure on the page. If the restore took nine hours against an objective of four, either the method changes or the objective does, and the owner is told which.
Put the figures in the agreement with whoever hosts the system as well. On the systems we host, the recovery plan is sized to how much downtime the business can tolerate, and how far back we can restore and how quickly are written into the hosting agreement.
Go back to the list when a system is replaced, when a process changes, after an acquisition, and after every outage and every test.
Common questions
What is the difference between RTO and RPO? RTO is how long the system may be down. RPO is how much recent work may be lost, measured as time back from the failure. A system can come back quickly and still have lost a day of entries, so each needs its own figure.
Every department says its system can never be down. What do we do? Show what that costs. Bring two or three options, each with the downtime and data loss it allows and its price, and ask the owner and the budget holder to pick one.
Does moving to the cloud take care of recovery? No. The cloud provider keeps its own infrastructure running. Backups of your data, a second copy somewhere else and the steps that bring your application back are things you set up and pay for.
How often should we test a recovery? After any significant change to the system or to how it is backed up, and often enough that the people who would do the recovery have done it before. For the systems at the top of the list, put a test on the calendar at least once a year.
If you cannot say how a system would be recovered because nobody can fully describe how it is built and hosted, a System Evaluation gives you an independent written account of its infrastructure, backups and delivery for a fixed fee.