In the first 90 days, map the acquired company’s chart of accounts to yours, decide what moves to your ERP and in what order, and rehearse the move before you make it. Until the cutover, the acquired business keeps running on the systems it has. For a small company with a business like yours, the cutover itself can fit inside that window. For a larger one, ninety days is a planning window, and a good result is a stable business, combined reporting and a tested plan.
The sections below are in order, and each depends on the ones before.
Start from a stable business and a full inventory
While you plan the move, the acquired business stays on the systems it has. That takes a second person with administrator access to their ERP and its database, no changes that are not essential, and a full copy of their data that has been restored once. Find the dates when their licenses, hosting and support end, and confirm the dates and what transfers with whoever handled the deal’s contracts. If the seller is running systems for you under a transition services agreement, its end date is your real deadline.
Before you decide what moves, record their ERP, its version and every customization, every system connected to it, and the reports and spreadsheets the business runs on. Write down where their processes differ from yours. Pricing, units of measure, the fiscal calendar, when revenue is recorded and how sales tax is charged are the usual places. What should IT map before integrating an acquired company’s applications? has the full list.
Map their chart of accounts to yours before anything moves
- Map their chart of accounts to yours in a table finance can read. The mapping is a set of decisions, and finance has to approve them.
- Load their trial balance into your reporting each month through that mapping. This gives combined numbers while both ERPs keep running.
- Write down the definitions that differ and which one the combined company will use. Two companies rarely mean the same thing by revenue or by an active customer.
- Reconcile the combined figures to their own reports. A difference found now is a mapping to fix, and it is much harder to trace after the cutover.
- Trace one sale from the register or the order to the general ledger in each company. Compare what the customer was charged, what was posted and what was remitted, and do the same for one purchase and one payroll run. A difference in posting rules does not show up as an error.
How do you combine an acquired company’s data with yours and keep the audit trail? covers the mapping tables and the reconciliation in full.
Decide what moves, and in what order
- Decide whether they move at all. We would move a company onto your ERP when it does the same kind of business the same way. When it does not, connecting the two at the ledger is often the better answer.
- Go through each process and sort it. Order to cash, purchasing, inventory and the close each fall into one of four groups: your ERP handles it as it is set up today, it needs configuration, it needs an extension, or the acquired company changes how it works.
- Move open transactions and master records, and keep closed history readable somewhere else. Rewriting years of another company’s history to fit your structure adds work and removes traceability.
- Give each of their integrations a decision and a name. Each is rebuilt against your ERP, replaced by one you already run, or retired.
- Check that your ERP has room. Licenses, legal entities, locations, tax jurisdictions and currencies may all need to be added before the first test.
Rehearse the cutover
- Run a trial migration with real data into a test copy of your ERP, and reconcile it. The first trial usually finds mappings that are wrong.
- Have people from the acquired company do a day of their real work in the test system. They will find what the process review missed.
- Pick the date around their calendar. Just after a month-end close and outside their busy season is the usual choice.
- Agree who can call a return to the old system, and until when. Decide it before the weekend of the cutover.
- Tell their people who to call in the first weeks. They have just lost the system they knew.
Common questions
Should every acquired company move onto our ERP? No. Move a company that does the same kind of business the same way you do. When its business is very different, or it may be sold again, leaving it on its own ERP and combining the numbers at the ledger is often the better answer.
Can the whole move be finished in 90 days? Sometimes, for a small company with few integrations and a business like yours. For a larger one, a good result at ninety days is a stable business, combined reporting and a rehearsed plan. A cutover date chosen before you know what the company runs is a guess.
Who should lead the work, IT or finance? Both have decisions only they can make. Finance owns the account mapping, the definitions and the sign-off on balances. IT owns the systems, the data and the cutover. Name one person who can settle a disagreement between them quickly.
What if the seller’s support for the old systems ends before we are ready? Raise it as soon as you see it, because an extension is easier to arrange early. The other option is to take over the old ERP as it is, in your own environment, and move the company onto yours later.
If the acquired company’s integrations are the part nobody has a plan for, Integrations & APIs describes how we map and rebuild them, starting with a fixed-fee System Evaluation.